SCI99 Editor

Apr 26, 2024 08:47:16

Zhejiang Liuheng Terminal Enters External Tank Construction

On April 23, at the construction site of the Zhejiang Energy Zhoushan Liuheng LNG receiving terminal, all four storage tanks had completed the foundation pouring, signifying that the tank construction had moved from the foundation phase to the external tank construction phase.

Liuheng LNG receiving terminal is located in Ningbo City, Zhejiang Province, and is planned to be completed and put into operation in June 2026. The receiving capacity will be 6 Mtpa, and will feature a 150,000-ton LNG vessel-specific berth, four 220,000 m3 storage tanks, and corresponding process facilities. The main project construction started in September 2022.

Ningbo is one of the concentrated investment areas for LNG receiving terminals in East China. Currently, the Ningbo area has an LNG receiving capacity of 11 Mtpa, and it is expected that by 2025 and 2026, there will be an incremental in receiving capacity of 9.5 Mtpa and 13 Mtpa, respectively.

Zhejiang Energy Group Co., Ltd., established in 2001, is mainly engaged in power source construction, electric and thermal power production, development and trade circulation of petroleum, coal, and natural gas, energy technology, energy services, and energy finance, among other business operations. In 2023, the company supplied 11.9 BCM of natural gas.

All information provided by SCI is for reference only,which shall not be reproduced without permission.

Request Submission

Full name
Concerned industry
Energy
Chemical
Plastic
Rubber
Agriculture
Metal
Concerned service
Data
Report
Insights
Consulting
Event
Others
I’d like to receive SCI’s insights, data, reports, etc.